Construction Update: Le Domaine de l’Orangeraie Releases Update on Construction Progress


Le Domaine de l’Orangeraie would like to inform all trade partners and the general public of the progress of the construction project of new villas on La Digue Island.

Started in September 2013, the construction of 8 new villas is on track and all major construction is now complete. The final finishings are now being fitted, and completion is expected late January 2015. Please see below a work update.




Work progress 


  • Both blocks to house 4 villas each are totally erected, and the remaining work is pure finishing works 
  • Roof works are 90% finished on both blocks 
  • Finishing works are progressing well, the new residence concept is due early 2015 
  • The access bridge to the villa is 75% completed, the access to the residence villa is from the garden  villa area leading to the new edifice. 
  • The first mock up floor is completed, and more details are forthcoming. 

 As the major Construction work is now completed, guests are not expected to be disturbed during the actual operation of the hotel. 


PLEASE NOTE: Name change 

Le Domaine de L’Orangeraie announces name change of the Residence villas, from ‘Family Residence 
villas’ to ‘’Garden Suite Residence’’. 

The name change comes at an opportune time before the villa opening and the new name matches the concept. 

We will ask you to change in your system to reflect the correct name.  



Contact your Masons Travel Representative to for rates and packages. 

www.masonstravel.com   |   webenquiry@masonstravel.com


     
Sign up for our Newsletter: http://eepurl.com/MAEFD